Construction Planning and Management

Page Length : 34

QuestionNo.01 In time-cost optimization of a project, crashing is done.

  • (A) On all the activities
  • (B) On all the activities lying on the critical path
  • (C) Only on activities lying on the original critical path and having flatter cost slopes
  • (D) On original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope

Answer: Option D

QuestionNo.02 Which of the following does not represent an activity?

  • (A) Site located
  • (B) Foundation is being dug
  • (C) The office area is being cleaned
  • (D) The invitations are being sent

Answer: Option A

QuestionNo.03 In resources leveling

  • (A) Total duration of project is reduced
  • (B) Total duration of project is increased
  • (C) Uniform demand of resources is achieved
  • (D) Cost of project is controlled

Answer: Option C

Additional information

Product Name

Construction Planning and Management Workbook

Product Size

701 KB

Format

File Format

File Category

DEPARTMENT/COURSE

Need For

College, Competition, Entrance, ESE, GATE, IES, PSU, Semester

Product Type

Provided By

Bush RC (NIT Agartala)

Uploaded By

Roop Chandra

Languages

English

Reviews

There are no reviews yet

Add a review
Construction Planning and Management Workbook Construction Planning and Management Workbook
Rating*
0/5
* Rating is required
Your review
* Review is required
Name
* Name is required
Add photos or video to your review
No more offers for this product!